INTRODUCTION 
      The 11.8 km Route 3 Country Park Section 
        expressway is divided into four major distinctive sections: Ting Kau Bridge 
        and the approach viaduct, the road section leading to the southern entrance 
        of Tai Lam Tunnel, the Tai Lam Tunnel, and the approach road and interchange 
        system at the northern end of the tunnel. This is the most complex highway 
        and tunnel system in Hong Kong. 
                The 880-metre waterway 
        of the Rambler Channel, which separates the Tsing Yi Island and Ting Kau, 
        is now connected by a cable-stayed bridge which is supported by three 
        independent towers. The foundation of the towers is composed of large-diameter 
        bored piles, anchored to provide better stability in resisting wind. The 
        structure of the towers was constructed in slipforms with the use of 65 
        mpa high-strength concrete. 
                Between Ting Kau 
        Bridge and Tuen Mun Highway there is a 510 m approach viaduct that spans 
        Castle Peak Road and Tuen Mun Highway before it reaches the road sections 
        leading to the southern entrance of Tai Lam Tunnel. This approach viaduct 
        was constructed of box-section, cast-in situ concrete by a balanced cantilever 
        method with the use of a traveler formwork system. A slip road made of 
        precast concrete beams supported on high level piers and portals leads 
        traffic from Tuen Mun Highway to Tai Lam Tunnel. 
                The 3.8 km Tai 
        Lam Tunnel consists of three tubes. Two tubes handle three lanes of traffic 
        each, while the smaller diameter middle tube is a servicing duct for ventilation 
        and maintenance purposes. The Tai Lam Tunnel was excavated using the drill-and-blast 
        method. The contractor employed a series of computer-operated drilling 
        rigs so that the drilling pattern could be accurately calculated. The 
        drill holes were then filled with emulsion compound and gassing agent 
        to produce the necessary explosion. The crushed rock was excavated and 
        transported to the exit of tunnel by conveyor belt for disposal. The progress 
        of excavation was about 5 m per day at the peak. As soon as the excavation 
        was completed, a concrete lining was formed by the use of a large mechanical 
        form system so as to strengthen and seal the exposed rock surface permanently. 
                The tunnel excavation 
        started simultaneously at both north and south ends. The works at the 
        south and north ends were carried out by Dragages and Nishimatsu, respectively. 
        Unlike other tunnel designs, there is a ventilation building on both ends 
        of the Tai Lam Tunnel. This building is so designed that it also serves 
        as the entrance to the Tunnel. 
                There is a 6.2 
        km approach road leading traffic from the northern end of the Tai Lam 
        Tunnel to Au Tau through Kam Tin area. In addition to the construction 
        of the approach road, this part of the project also included the construction 
        of the toll square and the administration building for the tunnel joint-venture 
        consortium, as well as a slip road and interchange system leading to Yuen 
        Long Bypass and Kam Tin Road. 
                As for the construction 
        of the approach road, there were several major rock cuts between Shek 
        Wu Tong and Ko Po. Difficulties encountered in this part of work were 
        mainly due to the scale of rock cutting as well as some major fractures 
        in the cut rock requiring further stabilisation using anchor systems. 
      main contractor 
        Route 3 Contractors Consortium 
        Nishimatsu Construction Co Ltd/Dragages et Travaux Publics (HK) Ltd 
         
         
     |