               PUBLIC 
                HOUSING 
                With the ground floor completed and the slab of first floor still 
                under temporary support, the steel reinforcement fixing for the 
                first floor wall is almost completed. Timber forms will then be 
                erected after the steel is inspected by an engineer. Note the 
                special formwork used on the in situ reinforced concrete facade 
                on the external wall. The facade for the upper floors is constructed 
                using precast units instead of forming by in situ method 
              |